Cringle Dock, Battersea

Date

Client

Size

Value

Stages

Sustainability

2015-2016

Battersea Power Station & WRWA

55,000 sm

£320m Estimated

RIBA Stages 1-2

Target BREEAM Excellent

  • Air-rights joint venture to deliver accommodation above a working wharf

  • Day-to-day lead on design and consultant coordination

  • Submitted for a successful outline consent in only 7 months

  • Major contribution to the triaged/reduced scheme that achieved consent first time at Wandsworth Planning Committee

  • When it became clear "Apple" were to be the single tenant for the entire Power Station office - produced a credible pitch for an air-rights office with overhead structure, where the office massing itself was the bridge across the wharf